Snorre has been producing oil and gas since August 1992
Statoil is today, on behalf of the Snorre Unit partners, submitting the plan for development and operation (PDO) of the Snorre Expansion Project to the authorities. At the same time, contracts worth up to NOK 9 billion will be awarded.
The investment will increase recovery from the Snorre field by close to 200 million barrels.
âSnorre Expansion has been a marginal project, and Statoil has worked closely with partners and suppliers to realise it. We have finally arrived at a good concept utilising existing infrastructure and reducing costs,â says Margareth Ăvrum, executive vice president for Technology, Projects and Drilling.
âIn 2017, we have benefitted from a comprehensive improvement effort by Statoil and suppliers, and we have succeeded in realising development plans for Njord, Bauge, Johan Castberg and now Snorre Expansion, leading to investments of NOK 90 billion on the Norwegian continental shelf (NCS) and important activity for the industry,â says Ăvrum.
The Snorre field is important in our effort of increasing long-term value creation and activity on the NCS. The life of Snorre A was originally expected to last until 2011â2014. Now the Snorre field is expected to produce beyond 2040.
âLong-term activity and value creation on the NCS is central in our strategy. Snorre Expansion is the largest improved oil recovery project (IOR) on the NCS, and provides valuable production and activity benefitting the company, partners and society. Investment costs slightly exceed NOK 19 billion, and the PDO involves a comprehensive subsea development, upgrading of the Snorre A installation, increased gas injection and gas import for injection,â says Arne Sigve Nylund, Statoilâs executive vice president for Development and Production Norway.
In addition to the PDO being submitted today, Statoil is also signing contracts for the subsea production system with TechnipFMC, fabrication and installation of the pipeline bundle system with Subsea 7, modification work on Snorre A with Aibel and a rig with Transocean. All contracts are subject to final approval of the PDO by Norwegian authorities.
âDuring the past years, Norwegian suppliers have demonstrated both a will and ability to change. Due to enhanced competitiveness, Norwegian industry plays a key role also in the Snorre Expansion project. We estimate that 80 percent of the investments will include companies in Norway. Competitiveness has a short shelf-life however, and it is vital that the improvement work continues with unabated strength,â says Ăvrum.
Based on analyses from Agenda Kaupang, around 23,000 man-years will be carried out in Norway in the Snorre Expansion Project phase.
Snorre Expansion plans to start production in 2021, and will be operated and maintained by the existing Snorre organisation in Stavanger, while supplies will still be handled by Fjordbase in Florø.
Partners in the Snorre field are: Statoil Petroleum AS (33.27%), Petoro AS (30%), ExxonMobil Exploration and Production Norway AS (17.44%), Idemitsu Petroleum Norge AS (9.6%), DEA Norge AS (8.57%) and Point Resources AS (1.1%).
Press conference at 10:00 CET
The press will be invited to a press conference for the Snorre Expansion PDO submittal and for signing of contracts at Statoilâs offices at Forus West at 10:00 CET.
If you have any questions or would like to register for the press conference, please contact: Eskil Eriksen, mobile: 95 88 25 34, email: eseri@statoil.com
Snorre has been producing oil and gas since August 1992
Statoil awards long-term subsea contracts on the Norwegian continental shelf to Aker Solutions, TechnipFMC og OneSubsea.
Submitting plan for development and production, and awarding Johan Castberg contracts.