Power cable being installed at Johan Sverdrup makes field best in class for CO2 emissions
The laying of the cable supplying Johan Sverdrup with power from shore started last week. This helps make the North Sea giant one of the oil and gas fields with the lowest CO2 emissions worldwide.
On Wednesday last week the cable-laying vessel NKT Victoria began laying the cables that will supply the Johan Sverdrup field with power from shore.
The starting point was the Johan Sverdrup converter station at Haugsneset near KĂ„rstĂž, and by the end of May the vessel will have laid nearly 200 kilometres of power cables out to the field in the North Sea.
Bundled with the power cables, a fibre-optic cable will once installed ensure good communication and enable monitoring and, when required, remote control of parts of the Johan Sverdrup fieldâs operations from shore.
âWe are now laying the very lifeline of the Johan Sverdrup field, which will supply the field with power from shore for more than 50 years,â says Trond Bokn, senior vice president for Johan Sverdrup.
The power cables will help make Johan Sverdrup one of the most carbon-efficient oil and gas fields in the world. Estimated at just 0.5 kg of CO2 per barrel, the emissions from Johan Sverdrup are about 20 times lower than the average on the Norwegian continental shelf, and 30 times lower than the international average.
This makes Johan Sverdrup a key project to help deliver on Statoilâs ambition of reducing annual carbon emissions by 3 million tonnes by 2030, compared with the estimated emissions.
âThe world is facing considerable challenges ensuring access to enough energy while doing so in a more climate-friendly way. Here Johan Sverdrup will play an important role: over the next 50 years, the fieldâs considerable reserves will be used to produce significant amounts of energy with low CO2 emissions,â says Bokn.
The CO2 emissions avoided as a result of Johan Sverdrup using power from shore add up to more than 400,000 tonnes of C02 per year, equivalent to the emissions of some 200,000 cars each year.
Several additional measures have been implemented to further reduce emissions during the Johan Sverdrup development. The cable-laying vessel NKT Victoria was designed to be supplied with power from shore while in harbour.
The mobile accommodation vessel «Haven», in use at the field from June onwards, has also been modified to utilise power from shore while in service at the Johan Sverdrup field. And based on current plans, the Johan Sverdrup field will be powered from shore already this autumn so that all the fieldâs power needs during the remaining hook-up and finalisation phase will be met with electricity supplied from shore.
âWeâve worked systematically to take advantage of the opportunities which the power from shore solution has given us. As a result, I believe weâve been able to reduce the carbon emissions from the field to the minimum,â says Geir Bjaanes, responsible for subsea, power and pipelines for the Johan Sverdrup project.
âBefore we get to that stage, however, we need to stay focused on the hectic installation period ahead of us. For the next three weeks or so we will be laying almost 10 kilometres of cables every single day. We have spent much time together with NKT preparing for this, but this will put our skills to the real test, our number one priority being safety and ensuring high quality in execution,â says Bjaanes.
After the cables reach the Johan Sverdrup field at the end of May, the next step will be to pull the cables in to the riser platform, where the converter station for the first phase of the development is located. Then the cables will be connected, before preparations and testing of the system start. And in the autumn of 2018, the Johan Sverdrup field should be ready to be powered with electricity from shore.
After the start-up of the second phase of the development in 2022, the Johan Sverdrup field will also enable power from shore to reach the remaining fields on the Utsira High â Edvard Grieg, Gina Krog and Ivar Aasen.
Related pages and downloads
- By using power from shore, instead of gas turbines, CO2 emissions from the production of oil and gas from Johan Sverdrup are estimated at just 0.5 kg CO2 per barrel which is more than 80% lower than the alternative. The CO2 emissions avoided per year are estimated to amount to more than 400,000 tonnes of CO2 per year, totalling almost 20 million tonnes of CO2 over the life of the field.
- The other fields on the Utsira High that will be supplied with power from shore after the start-up of the second phase of the Johan Sverdrup development are Edvard Grieg (operator: Lundin Norway), Gina Krog (operator: Statoil), and Ivar Aasen (operator: Aker BP).
- Other fields on the NCS that are or will be powered from shore include GjĂža (operator: Neptune Energy), Martin Linge (operator: Statoil), Troll A (operator: Statoil) and Valhall (operator: Aker BP).
- In the first phase of the Johan Sverdrup development the electrical equipment (HVDC) for the converter stations both at Haugsneset and on the riser platform is delivered by ABB. All work related to the construction of the converter station at Haugsneset is done by Aibel. NKT is responsible for the delivery and installation of the power cables for the Johan Sverdrup field.
- In the second phase of the Johan Sverdrup development, Siemens has been awarded the contract for delivering the electrical equipment (HVDC) for the converter stations both onshore and on the Johan Sverdrup field centre.
- Johan Sverdrup is one of the five biggest oil fields on the Norwegian continental shelf. With expected recoverable resources of between 2.1-3.1 billion barrels of oil equivalent, it will be one of the most important industrial projects in Norway over the next 50 years.
- Johan Sverdrup will be developed in several phases. Phase 1 is expected to start up in late 2019 with production capacity estimated at 440,000 barrels of oil per day.
- Phase 2 is expected to start up in 2022, with full field production estimated to peak at 660,000 barrels of oil per day. Peak production on Johan Sverdrup will be equivalent to 25% of all Norwegian petroleum production. The plan for development and operation (PDO) for phase 2 will be submitted before September 2018.
- PARTNERS: Statoil 40.0267% (operator), Lundin Norway 22.6%, Petoro 17,36%, Aker BP 11.5733% and Maersk Oil (a Total company) 8.44%.