Further increasing value of Johan Sverdrup
Statoil and partners further increase the value of the Johan Sverdrup field as a result of continued high quality in project execution, good drilling efficiency and further maturation of the resource base.
The Johan Sverdrup development is now nearly 70% complete, which is according to plan, and investment costs are continuing its positive trend.
Phase 1 of the project is currently estimated at NOK 88 billion (capex numbers in nominal terms based on fixed currency), which amounts to a reduction of NOK 35 billion or close to 30 percent since the plan for development and operation (PDO) was approved in August 2015.
Break-even is reduced to below USD 15 per barrel for the first phase of the Johan Sverdrup project.
âJohan Sverdrup is a world-class project and continues to deliver. There is high quality in project execution, the costs are decreasing, and the resource estimate goes up. Johan Sverdrup is now even more robust and valuable for both the partners and society. This is a result of good cooperation between Statoil, our partners and suppliers,â says Margareth Ăvrum, executive vice president for Technology, Projects & Drilling in Statoil.
âJohan Sverdrup is also benefiting from the drilling and well improvement programme in Statoil. Weâve drilled more wells than planned, more than one year ahead of plan, which has contributed greatly to cost reductions in the project. The wells also make our production plans even more robust and have improved our knowledge of the reservoir. Based on this, we are now able to increase the resource estimate for Johan Sverdrup further,â continues Ăvrum.
Since the PDO for the first phase was submitted the range of the full-field resource estimate has improved from 1.7-3.0 to now 2.1-3.1 billion barrels of oil equivalents.
The Johan Sverdrup project will be developed in several phases, and the PDO for phase 2 will be submitted to Norwegian authorities in the second half of 2018. Further maturation has reduced the estimated investment costs for phase 2 to below NOK 45 billion.
With this, the break-even for the full-field development of Johan Sverdrup has been improved to below USD 20 per barrel.
âThe standardization of equipment packages, copying of good solutions, and doing things right the first time â in collaboration with our suppliers â has been critical to the positive developments that we see in the first phase of Johan Sverdrup. In phase 2 we are taking this one step further, and we are starting to see the results of thisâ, says Kjetel Digre, project director for Johan Sverdrup in Statoil.
A more streamlined operation and maintenance model, combined with increased use of digital and automated solutions, has also helped reduce estimated yearly operating costs by nearly NOK 1 billion or approximately 30 percent since the PDO was approved in August 2015.
âJohan Sverdrup and its 50-year lifespan is a unique opportunity to think big and differently about new solutions. A lot of this â for example sensors that measure the condition of important equipment, or fiberoptic reservoir monitoring â are technologies that we implement from day one. However, it is also about equipping the field for possible future solutions that can further strengthen safety, efficiency and the value of the field over time,â states Digre.
- Johan Sverdrup is one of the five biggest oil fields on the Norwegian continental shelf.
- With expected recoverable resources of between 2.1-3.1 billion barrels of oil equivalent, it will be one of the most important industrial projects in Norway over the next 50 years.
- Johan Sverdrup will be developed in several phases. Concept decision for phase 2 was made last year and the selected concept consists of another process platform (P2), modifications to the riser platform and subsea production and injection systems. The plan for development and operation (PDO) for phase 2 will be submitted before September 2018.
- Phase 1 is expected to start up in late 2019 with production capacity estimated at 440,000 barrels of oil per day.
- Phase 2 is expected to start up in 2022, with full field production estimated at 660,000 barrels of oil per day. Peak production on Johan Sverdrup will be equivalent to 25% of all Norwegian petroleum production.
- PARTNERS: Statoil 40,0267% (operator), Lundin Norway 22,6%, Petoro 17,36%, AkerBP 11,5733% and Maersk Oil 8,44%.