Hammerfest LNG to resume operations in a week
The extensive repairs at Melkøya have been completed, but the run-up of the plant takes somewhat longer than planned.
During the weekend, a minor fault was discovered on a compressor that needs to be rectified prior to start-up. The component is now being replaced, and the stepwise process towards operations continues through the week.
"Hammerfest LNG has been prepared for production, but we are taking the extra time necessary to safely resume operations," says Grete B. Haaland, Equinor's senior vice president for onshore facilities.
Equinor announced on behalf of the partnership in January that the start-up of Hammerfest LNG had been scheduled for 17 May 2022. After an extensive repair and improvement work period, the plant has been prepared for ramp-up.
The partnership includes Equinor Energy AS, Petoro AS, TotalEnergies EP Norway AS, Neptune Energy Norway AS, Wintershall Dea Norway AS. Equinor is the operator of Hammerfest LNG.
Latest news
Equinor brings on another rig
Equinor has awarded a two-year firm contract to Northern Ocean Wind AS to employ the mobile rig Deepsea Bollsta on the Norwegian continental shelf.
Ex. dividend second quarter 2024 today - Oslo Børs
The shares in Equinor ASA (OSE: EQNR; NYSE: EQNR) will as from today be traded on Oslo Børs exclusive the second quarter 2024 cash dividend as detailed below.
bp, Equinor, Shell and TotalEnergies join forces to help increase access to energy
bp, Equinor, Shell and TotalEnergies announce a commitment to invest in support of the UN Sustainable Development Goal 7 (UN SDG7), which aims to ensure access to affordable, reliable, sustainable, and modern energy for all.